Data Center PDU & UPS Maintenance

From June 20, 2026, 9:00 a.m. to June 20, 2026, 5:00 p.m.

EXTENDED MAINTENANCE

Impact of the change on users:

The Data Center will be proactively placed on the generator during maintenance as a precaution to avoid any impact from an unexpected power interruption from public utilities. Once the maintenance is completed, we will switch back over to Dominion Power.

The UPS systems will be placed in maintenance bypass one at a time by the vendor technician for maintenance. After each UPS has been checked, the unit will be placed back online. All PDUs will remain online while units are checked individually.

Reason for the change:

The vendor is performing preventative maintenance on the PDU and UPS.